Review a ToR Budget
Review the actual evaluation budget/ceiling with TOR scope/methods, quantities/effort, schedule, currency/tax basis, dated cost evidence and procurement/funding rules. Request missing content before cost judgments; names are not rates or rules.
Check internal scope/quantity/effort/cost consistency. Assess market realism only from relevant dated quotes/benchmarks, otherwise unverified. A published TOR may legitimately give only a ceiling; do not demand confidential internal breakdowns. Check necessary personnel/travel/collection/analysis/reporting/overhead, context-specific sites/days and field rates, plus relevant translation/transcription/ethics/dissemination/production without assuming universal fees or double counting.
Assess contingency only where rules permit, with priced risk rationale and authorization; no default percentage or penalty for a prohibited line. Return short assessment, located dimension/rating/evidence/action table, prioritized revisions and conditional readiness advice. Use Meets, Needs Revision, Not Assessable or reasoned Not Applicable, numerical anchors only if supplied. Continue supported parts; unknown rates remain unknown rather than invented affordability or approval.
- Choose This Prompt When
- Use this to review an evaluation ToR's resource envelope. Choose Review ToR Readiness for the full solicitation, or Review a Budget vs Actuals Narrative for spending against an approved budget.
On this page
Worked Example
Illustration only. The setting and figures are invented to show the pattern.
Scenario: A midline evaluation ToR for a regional water and sanitation program states a budget ceiling of 90,000 USD. The commissioning team wants to know before issue whether the ceiling can buy the scope.
What You Give the AI: The ceiling and its currency, the scope and methods section (a household survey of 1,200 households, 12 focus groups, a team of two evaluators), a six-week fieldwork schedule, and a note that the ceiling includes tax. No quotes or past contract rates are attached.
What the AI Might Return: An overall rating of Needs Revision, with the table showing why. The survey row finds that 1,200 interviews in six weeks imply a field team size the budget never mentions. The translation row is flagged as missing from scope and cost alike. Market realism reads Not Assessable because no dated quotes were supplied. A readiness note says the ToR can issue once team size and translation are settled.
When to Choose This Prompt
- You hold a draft ToR and want to know whether the budget or ceiling fits the scope and methods before bidders see it.
- Quantities, schedule and budget came from different people and may disagree.
- You want a list of cost lines that the scope implies but nobody has priced.
When Not to Choose It
- You need the whole solicitation checked, including purpose, scope and delivery conditions. Review ToR Readiness
- You are looking at spending against an approved budget in a progress report. Review a Budget vs Actuals Narrative
- You are checking your own M&E budget for a proposal submission. Review M&E Budget Adequacy
Checking the Output
- Take each quantity in the scope (sites, interviews, days) and find it again in the AI's table. Any figure it quotes that your ToR does not contain was made up.
- Where the AI calls a rate realistic or low, look for the dated quote or benchmark you supplied. With none, the rating should read unverified.
- A ceiling-only ToR is legitimate. If the review demands a line-item breakdown from you, it has misread the document.
- Read the contingency comment against your funding rules. It should depend on what those rules allow and give a reason tied to a risk.
- Scan for double counting, such as training days in both personnel and fieldwork.
- Each rating should cite its evidence in your text.
Common Problems and Fixes
- The AI names typical day rates or percentages from memory. Fix: Use only the rates in your attachment and mark everything else Not Assessable.
- It rates the budget as sufficient without knowing the currency or tax basis. Fix: State both in your input and ask it to hold cost judgments until it has them.
- The review treats a missing breakdown as a defect. Fix: Say the ToR is published with a ceiling only, and ask for a check of scope against that ceiling.
- The output is a long essay with no table. Fix: Ask for the located table (dimension, rating, evidence, action) and a short list of priority revisions.
Adapting It to Your Context
- Evaluation with heavy remote data collection: Give the platform, license and enumerator payment arrangements so costs are not assumed from a field model.
- Strict procurement rules on contingency: Paste the rule text and ask whether a contingency line is allowed at all before size is discussed.
- Several lots or phases: Review one lot at a time and give the shared costs separately.
- Budget set by the funder before the design was done: Ask for a ranked list of what to cut if the scope cannot change.